Why the Lowest Remodeling Estimate May Not Be the Lowest Price
You’ve decided to remodel your home and have collected three estimates.
One contractor quotes $72,000. Another comes in at $81,000. The third estimates $88,000.
At first glance, the decision might seem obvious. Why would you pay $16,000 more for the same renovation?
But there’s a more important question:
Are they actually estimating the same project?
A construction estimate isn’t simply a price tag. It represents what a contractor believes the project will require—the labor, materials, preparation, inspections, subcontractors and potential problems that have been accounted for before work begins.
That’s why two seemingly similar estimates can be thousands of dollars apart.
And it’s also where change orders enter the picture.
What is a change order?
A change order is a documented modification to the original construction contract after work has begun. It can change the scope, materials, schedule and, frequently, the price of a project.
Change orders aren’t inherently bad.
Sometimes they’re unavoidable.
Sometimes the homeowner requests them: You decide you want different tile, move an electrical outlet or upgrade the countertops after construction has begun.
Other times, demolition reveals a condition nobody could reasonably have known existed.
The important distinction is between a genuine construction surprise and something that reasonably could have been investigated or accounted for before construction began.
Scenario #1: The problem nobody could see
Imagine you’re remodeling a bathroom.
Your contractor removes the shower surround and discovers that a slow plumbing leak has damaged framing inside the wall.
There was no visible staining. No obvious odor. No accessible evidence of the damage before demolition.
Now the project can’t simply continue as originally planned. Damaged materials may need to be removed, the source of the moisture repaired and portions of the wall rebuilt before the new shower can be installed.
That’s exactly the kind of situation in which a legitimate change order may be necessary.
The EPA specifically notes that mold and moisture problems can remain hidden behind drywall, wallpaper and paneling, underneath carpet and around pipes inside walls. US EPA
No estimate can guarantee that a contractor will know everything hiding inside a closed wall.
In fact, research on building renovations supports just how significant those surprises can be. A peer-reviewed study analyzing 517 change orders from 27 renovation projects found that unforeseen existing conditions produced significantly greater cost impacts than other causes of change orders. (Kyung Hee University)
That’s a construction unknown.
A homeowner should reasonably expect the contractor to explain what was discovered, why it changes the original scope, what additional work is required and how it affects the price and schedule.
But there’s another kind of “surprise.”
Scenario #2: The problem that could have been investigated
Suppose you’re renovating an older home and removing existing flooring.
Contractor A provides a lower estimate without addressing the possibility that the flooring or adhesive may contain asbestos.
Contractor B notices the age and type of material and recommends having suspect material evaluated before demolition. The estimate is consequently higher because it anticipates the possibility that special handling or additional work may be necessary.
Then construction begins.
If testing later confirms asbestos-containing material, Contractor A may now need to stop work and issue a change order.
Suddenly that inexpensive estimate isn’t necessarily inexpensive anymore.
The EPA recommends that when a renovation will disturb material suspected of containing asbestos—such as certain floor or ceiling tiles or older pipe wrap—the material should be sampled by a properly trained and accredited asbestos professional and analyzed by a qualified laboratory. You generally cannot determine whether a material contains asbestos just by looking at it. (US EPA)
That doesn’t mean every contractor should automatically include asbestos abatement in every renovation estimate. It means potential risks should be identified, discussed and, when appropriate, investigated before demolition starts.
The same principle can apply to signs of moisture intrusion. EPA remodeling guidance recommends addressing existing moisture problems before proceeding with certain remodeling work, and EPA guidance notes that experienced professionals can use tools such as moisture meters and borescopes when investigating suspected hidden mold. (US EPA)
That’s pre-construction due diligence.
And it costs money.
Why a more detailed estimate can cost more
Consider two hypothetical kitchen-remodel estimates:
Estimate A: $64,000
Demolition, cabinets, countertops, flooring, electrical, plumbing and painting.
Estimate B: $71,500
The same basic renovation—but this contractor has also accounted for additional electrical work identified during the site visit, plumbing modifications required by the new layout, floor preparation beneath the new flooring and testing of suspect material before demolition.
Estimate B appears to cost $7,500 more.
But suppose construction begins under Estimate A and those same issues emerge one at a time:
- Electrical modification: +$2,100
- Plumbing changes: +$1,900
- Floor preparation: +$2,000
- Environmental testing/related work: +$2,500
The $64,000 project has become $72,500.
The $71,500 estimate didn’t suddenly become cheaper.
It may simply have been more complete from the beginning.
Those numbers are illustrative, not industry averages.
Don’t compare the bottom line. Compare the scope.
This is probably the single most important thing homeowners should take away when comparing renovation bids.
If one contractor quotes $65,000 and another quotes $82,000, don’t immediately ask:
“Why is this contractor $17,000 more?”
First ask:
“What does the $82,000 estimate include that the $65,000 estimate doesn’t?”
Look at allowances. Materials. Permits. Demolition. Disposal. Site preparation. Electrical and plumbing work. Protection of existing finishes. Environmental testing when appropriate. Cleanup. Project management. Finish selections.
And pay attention to exclusions.
Sometimes the lowest estimate really is the best estimate.
Sometimes one contractor simply operates more efficiently or obtains materials at better prices.
But sometimes a large price difference exists because you’re comparing two different scopes of work that happen to have the same project name.
Questions to ask before signing a renovation contract
When estimates vary substantially, homeowners can ask each contractor the same questions:
- What exactly is included—and excluded—from this price?
- Which parts of the estimate are allowances rather than fixed costs?
- What potential problems did you identify during your inspection?
- Are there conditions we should investigate before demolition?
- What situations would require a change order?
- How are change orders priced and approved?
- Will I receive the price before additional work begins?
- What happens to the schedule if an unforeseen condition is discovered?
You’re not trying to eliminate every possible change order.
In renovation work, that isn’t realistic. Existing buildings can contain conditions nobody can see until they’re opened up.
What you can determine is how thoroughly each contractor investigated the project before giving you a price.
The cheapest estimate and the cheapest project aren’t always the same thing
A good estimate shouldn’t scare homeowners with every imaginable worst-case scenario.
Nor should it pretend those possibilities don’t exist.
The goal is to identify what can reasonably be identified, investigate conditions that warrant further examination, clearly define what is and isn’t included, and explain what happens if the project encounters something genuinely unexpected.
So when three contractors hand you three very different numbers, resist the temptation to compare only the totals.
Compare what those numbers actually buy.
Because sometimes the contractor who found more problems before construction begins is the contractor who gives you fewer surprises after it does.